Commitments to Project
| Description | Status | Due Date |
| Arrange for dumpster | Patricia Weld, DONE | Friday, May 25th, 2007 |
| Provide enough tarps to cover roof and walls | Ben Platnik, DONE | Saturday, May 26th by Noon |
| Remove fiberglass from roof | DONE | Saturday, May 26th by Noon |
| Peel back foam roof for clerestory wall | DONE | Saturday, May 26th by Noon |
| Remove fiberglass panels from walls | DONE | Saturday, May 26th by Noon |
| Clean exterior surfaces for construction | DONE | Saturday, May 26th by Noon |
| Clean up debris on site | DONE | Saturday evening, May 26th |
| Recycle anything of value | DONE | June 3rd, 2007 |
Crew Members
| Job | Person | Responsibilities |
| Crew Chief | Steve Bartram | Coordinate crew. Plan tasks. Arrange for tools and material. |
| Destructor | Michael Scott | Demo on Saturday May25th, 8am |
| Destructor | Eleaonor Batho | Demo on Saturday May25th, 8am |
| Destructor | Lou Guttierez | Demo on Saturday May25th, 8am |
Todo List (DONE)
Please bring gloves, wear hard soled shoes, and IF you have a cordless drill that would be swell. Water also.
- Remove plastic sheeting from roof - unscrew and lay out on walk above building. The sheeting will need to be cut and then put into the bin.
- Remove the cabinets from inside (four wall screws will be pried to allow 6 foot long cabinets to be set down) - we will move the cabinets to the patio for storage.
- Remove the 2x4 "cripples" from the overheads - about 20 will need to be knocked out - if we can salvage them fine otherwise they are throw aways. We have to have the roof off to determine this.
- Remove plastic side panels from sides.
- Remove air conditioner and store.
- Remove small door under air conditioner.