Scope

The Drywall work crew is part of the UUBG-007 Project: Replace Fiberglas Roof in Office The Drywall crew completes interior construction (windows, insulation). Installs sheet rock on new ceiling and existing walls. Tape and plaster seams. Texture? Prep for painting.

Summary (May 30th)

REV+2: Bill of material. Assignments and schedule.


Commitments to Project
Description Status Due Date
Bill of materials to Preparation crew Lou, DONE Wednesday, May 23th, 2007
Install new windows. DELAYED Saturday, June 3rd
Install fiberglass insulation in ceilings and walls. Assigned: Neil & Lou Wednesday, May 30th
Hang sheetrock on ceilings and walls. Assigned: Steve & Chris Saturday, June 2nd
Tape and mud sheetrock STATUS Sunday, June 3rd
Finish mud and texture? Prep for painting. STATUS Friday, June 8th
DESCRIPTION STATUS YYYY-MM-DD

NOTE:
The quality of the drywall finish does not need to be professional. The walls are mostly hidden. We can certainly improve on what's there now. This is a good chance to practice!!!

Crew Members
Job Person Responsibilities
Crew Chief Steve Bartram Coordinate crew. Plan tasks. Arrange for tools and material.
Drywaller Lou Guttierez Skilled drywall. Tape and mud. Bring tools.
Drywaller Cris Faller Skilled drywall. Tape and mud. Bring tools.
Avail. Sat June 2nd 8AM~3pm(latest) drywall.
Tape & Mud Eleanor Batho Drywall install. Tape and mud. Bring tools.
Insulator Neil Lynch Install fiberglass insulation. Bring special gloves.
Insulator Stu Anderson Install fiberglass insulation.
Labor Estimate
Who Task Description Hours
TITLE_OR_PERSONS DESCRIPTION_OF_ALL_NECESSARY_ACTIVITIES HOURS
WHO DESCRIPTION HOURS
---- TOTAL HOURS: SUM
Tools & Material
Item Source Material Description Qty & Units Cost
1 Dixieline 4x8 x 1/2" sheet drywall 17 @ $10 $170
2 Dixieline Drywall tape 250' roll 4 rolls@ $2.29 $8.24
3 Dixieline Drywall mud 5 boxes@ $6.80 $34.00
4 Dixieline Internal corner bead, 10ft 2 @ $2.06 $4.12
5 Dixieline Fiberglass Kraft face, R-19, 23", 118sqft 2 rolls @ $60.00 $120.00
6 Dixieline Fiberglass Kraft face, R-13, 15", 106sqft 1 rolls @ $40.00 $40.00
---- Buyer: Stu Anderson BOM Total: $SUM
Todo List
  1. ITEM
  2. ITEM
  3. ITEM
Action Items
Item Done Description Who When
1 ? Purchase Materials Stu Anderson Noon, Wednesday 2007-05-30
2 ? Install blocking Neil & Stu Wednesday 2007-05-30
3 ? Install fiberglass Neil & Lou Wednesday 2007-05-30
4 ? Pick up 14 sheets drywall, etc from Dixieline Lou Wednesday 2007-05-30
# ? DESCRIPTION WHO WHEN